Construction Activities: United States

Construction Activities: United States

Dates and times provided below may change due to weather conditions and other factors affecting construction activities. Although this list is intended to be comprehensive, unavoidable emergency road detours and road closures may occur. Please watch for workers when travelling in the area. We apologize for any inconvenience and thank you for your patience.

There are many ways to stay connected with us. We encourage open dialogue and will work to answer your questions. Follow the project on Twitter at www.twitter.com/WDBAbridge, like us on Facebook at www.facebook.com/GordieHoweBridge, and connect with us on LinkedIn at www.linkedin.com/company/wdba-apwd for updates on construction or call 1-844-322-1773.

Week of February 17, 2020

Construction Activites - What you need to know

Michigan Interchange I-75 Closures

As construction of the Michigan Interchange begins, Bridging North America will temporarily implement partial closures on the following streets for construction activities:

  • No closures scheduled between February 17 and February 23

US Port of Entry (POE)

  • Crews are continuing wick drain installation with approximately 22,000 complete out of 105,000 wick drains

Phase 2 US POE configuration remains. The perimeter of the site includes:

  • Post St eastward to Dragoon St, and from Jefferson Ave northward to the Norfolk Southern Railroad tracks (NSR).
  • Livernois Ave between South St to NSR and South St between Livernois Ave and Dragoon Street continues to remain open. Access will be maintained to adjacent properties.

US Bridge site

  • The US Bridge team started installation of the 18 tower and the backspan 3m drilled shafts. Work plan development continues for construction tower footings in spring 2020

 

 

 

 

 

 

 